   Of the 61 eligible LGUs, 37 signified intent to avail of the Project, hence the revised target for capability building component is 37 LGUs.

 

 

 

   The program of activities was modified incorporating the activities of the PMO in the evaluation and monitoring of sub-project proposals and incorporating the above stated changes.

 

   Technical assessment  

On objectives

   The Project objective in developing the capabilities of the eligible LGUs was substantially achieved. The Project accomplished 116 percent in terms of providing capability building on project development to the LGUs and 156 percent in terms of number of participants. The post training assessment of the participants for the resource speakers and the training program as a whole were between very good to excellent. The participants further confirmed the rating during the closing programs when they rendered their impressions and insights.

On results

 


   The capability building program improved the capabilities of the LGUs in preparing project proposals. The program has developed their confidence in project development. Six out of the 37 recipient LGUs prepared and submitted sub-project proposals to the PMO for the ASSEF Project as of September 30, 2006.


On assumptions/hypotheses

 


   still valid
 

 


On activities

 


  
Of the six activities, only two activities were undertaken during the period under review. The first activity – implementation of project development training was substantially conducted by the PMO with 116% accomplishment in terms of target LGUs and 156% in terms of target participants. For the second activity – visualization of the preparation of micro project proposals, the PMO received six micro project proposals from the participating LGUs. The PMO conducted the initial evaluation of the sub-project proposals and forwarded the evaluation reports to the proponents. The PMO conducted technical assistance upon request to the LGUs in the revision of the sub-project proposals. The remaining activities will be undertaken starting October 2006.

 


On expenses made

   The expenses made pertains to the purchase of supplies, reproduction of handouts, meals and accommodation for the participants, gasoline used for the transport of resource speakers and participants as well as the honoraria of the resource persons for the capability building training.  It also includes the cost of laptop and multi-media and the purchase of vehicle used during the last batch of Capability Buiding Training and for monitoring of sub-projects.

On the counterpart

   The NEDA 5 provided counterpart to the Project during the period in the amount of P 1,915,497.73 (see annex NEDA Counterpart to ASSEF Project, March-September 2006 Progress Report)