PROJECT IMPLEMENTATION


IMPLEMENTATION ARRANGEMENTS

   The Project wIll be coordinated by NEDA 5 Office through a PMO under the guidance of the Project Sterring Committee (PSC). The sub-projects will be  implemented by the LGUs.

The PSC is chaired by a Deputy Director General of NEDA and the members will be AECI Coordinator General in the Philippines and the Regional Director of NEDA 5.
 
   The NEDA 5 through the PMO will coordinate the implementation of the project. The PMO has a core staff (full time) and a support staff (on need basis) from NEDA 5, AECI and two direct hired staff. The Core staff is composed of officials from AECI and NEDA 5. AECI may assign a Co-Manager for the Project. The staff complement of the PMO from NEDA 5 (salaries paid by NEDA) are as follows:

  • NEDA 5 Assistant Regional Director - Co-Manager

  • Assistant Manager

  • Administrative Officer

Technical Staffs - 28
Non-Technical Support Staff - 15
Direct Hired Staff - 2 (technical and 1 assistant finance officer)

   The sub-projects will be implemented by the LGUs and the mode of implementation is by administration.  

  • Implementer - Municipal Mayor assisted by Local Project Officer

  • Project Monitoring - MPDC/Local Project Monitoring Committee

POSSIBLE LOCAL PROJECT OFFICER

  • Agriculture/Fishery - Municipal Agriculturist

  • Post Harvest/Agriculture support Facilities - Municipal Engineer/Municipal Agriculturist

  • Domestic Water Supply - Municipal Engineer

  • Pre-elementary/Day Care - Municipal Social Welfare Development Officer

  • Coastal Resource Management and Watershed Management- Environment Officer 

   The other officers of the LGUs that may be involved in the Project include : MPDC; Municipal Treasurer; Municipal Accountant, Budget Officer; Municipal Engineer; MSWDO; Municipal Health Officer; Municipal Agriculturist; Municipal environment Officer among ohters.

IMPLEMENTATION OF ACTIVITIES

Planned activities for the period reported

Degree of implementation

Activity # 1
Description
Implementation of project development training Four batches of training on project development cum detailed orientation on ASSEF Project conducted by the PMO for the LGUs
Resources

Four management staff, 28 technical staff, 15 non-technical staff, two direct hired staff. Equipment: vehicle; lap-top and desk top computers, printers, multi-media system & scanner

Costs

Total cost – Php 3,614,386.51

AECI counterpart – Php 1,698,888.78 and NEDA 5 counterpart – Php 1,915,497.73

Activity # 2
Description

Visualization of the preparation of micro project proposals

Evaluation of sub-project proposals – 12 proposals received from LGUs

Resources

Three management staff, six technical staff and two direct hired project staff. Computers and printers used by the management and the technical staff
Costs Preliminary evaluation cost of about Php 10,000 per sub-project or a total estimated cost of Php 60,000 for six sub-projects

Activity # 3

Description

Preparation of the technical-financial work plan

None – to be undertaken starting fourth quarter of 2006
Resources  
Costs  

Activity # 4

Description

Evaluation and/or revision of micro project proposals

None – to be undertaken starting fourth quarter of 2006

Resources

 

Costs

 

Activity # 5

Description

Implementation of micro projects

None – to be undertaken by the LGUs and the PMO starting 2007

Resources

 
Costs  
Activity # 6
Description

Monitoring of micro projects implementation

None – to be undertaken by the LGUs and the PMO starting 2007

Resources

 

Costs

 


Technical assessment

      On objectives

      The Project objective in developing the capabilities of the eligible LGUs was substantially achieved. The Project accomplished 116 percent in terms of providing capability building on project development to the LGUs and 156 percent in terms of number of participants. The post training assessment of the participants for the resource speakers and the training program as a whole were between very good to excellent. The participants further confirmed the rating during the closing programs when they rendered their impressions and insights.

      On results

 

      The capability building program improved the capabilities of the LGUs in preparing project proposals. The program has developed their confidence in project development. Six out of the 37 recipient LGUs prepared and submitted sub-project proposals to the PMO for the ASSEF Project as of September 30, 2006.  

 

   On assumptions/hypotheses


 
   still valid


   On activities


     
Of the six activities, only two activities were undertaken during the period under review. The first activity – implementation of project development training was substantially conducted by the PMO with 116% accomplishment in terms of target LGUs and 156% in terms of target participants. For the second activity – visualization of the preparation of micro project proposals, the PMO received six micro project proposals from the participating LGUs. The PMO conducted the initial evaluation of the sub-project proposals and forwarded the evaluation reports to the proponents. The PMO conducted technical assistance upon request to the LGUs in the revision of the sub-project proposals. The remaining activities will be undertaken starting October 2006.


   On expenses made

   The expenses made pertains to the purchase of supplies, reproduction of handouts, meals and accommodation for the participants, gasoline used for the transport of resource speakers and participants as well as the honoraria of the resource persons for the capability building training.  It also includes the cost of laptop and multi-media and the purchase of vehicle used during the last batch of Capability Buiding Training and for monitoring of sub-projects.

   On the counterpart

   The NEDA 5 provided counterpart to the Project during the period in the amount of P 1,915,497.73 (see annex NEDA Counterpart to ASSEF Project, March-September 2006 Progress Report)