The Project wIll be coordinated
by NEDA 5 Office through a PMO under the guidance of the Project
Sterring Committee (PSC). The sub-projects will be
implemented by the LGUs.
The PSC is chaired by a
Deputy Director General of NEDA and the members will be AECI
Coordinator General in the Philippines and the Regional Director
of NEDA 5.
The NEDA 5 through the PMO will coordinate the implementation of
the project. The PMO has a core staff (full time) and a
support staff (on need basis) from NEDA 5, AECI and two direct
hired staff. The Core staff is composed of officials from AECI
and NEDA 5. AECI may assign a Co-Manager for the Project. The
staff complement of the PMO from NEDA 5 (salaries paid by NEDA)
are as follows:
Technical
Staffs - 28
Non-Technical Support Staff - 15
Direct Hired Staff - 2 (technical and 1 assistant finance
officer)
The sub-projects
will be implemented by the LGUs and the mode of implementation is by
administration.
POSSIBLE
LOCAL PROJECT
OFFICER
-
Agriculture/Fishery - Municipal Agriculturist
-
Post
Harvest/Agriculture support Facilities - Municipal
Engineer/Municipal Agriculturist
-
Domestic Water
Supply - Municipal Engineer
-
Pre-elementary/Day Care - Municipal Social Welfare Development
Officer
-
Coastal
Resource Management and Watershed Management- Environment
Officer
The
other officers of the LGUs that may be involved in the Project
include : MPDC; Municipal Treasurer; Municipal Accountant, Budget
Officer; Municipal Engineer; MSWDO; Municipal Health Officer;
Municipal Agriculturist; Municipal environment Officer among ohters.
IMPLEMENTATION
OF ACTIVITIES
|
Planned activities for the period reported |
Degree of
implementation
|
|
Activity
# 1 |
|
Description |
|
Implementation of project development training |
Four
batches of training on project development cum detailed
orientation on ASSEF Project conducted by the PMO for the
LGUs |
|
Resources |
Four
management staff, 28 technical staff, 15 non-technical
staff, two direct hired staff. Equipment: vehicle; lap-top
and desk top computers, printers, multi-media system &
scanner |
|
Costs |
Total
cost – Php 3,614,386.51
AECI
counterpart – Php 1,698,888.78 and NEDA 5 counterpart – Php
1,915,497.73 |
|
Activity
# 2 |
|
Description |
|
Visualization of the preparation of micro project proposals |
Evaluation of sub-project
proposals – 12 proposals received
from LGUs |
|
Resources |
Three
management staff, six technical staff and two direct hired
project staff. Computers and printers used by the management
and the technical staff |
|
Costs |
Preliminary evaluation cost of about Php 10,000 per
sub-project or a total estimated cost of Php 60,000 for six
sub-projects |
|
Activity
# 3 |
|
Description |
|
Preparation of the technical-financial work plan |
None – to
be undertaken starting fourth quarter of 2006 |
|
Resources |
|
|
Costs |
|
|
Activity
# 4 |
|
Description |
|
Evaluation and/or revision of micro project proposals |
None – to
be undertaken starting fourth quarter of 2006 |
|
Resources |
|
|
Costs |
|
|
Activity # 5 |
|
Description |
|
Implementation of micro projects |
None – to
be undertaken by the LGUs and the PMO starting 2007 |
|
Resources |
|
|
Costs |
|
|
Activity
# 6 |
|
Description |
|
Monitoring of micro projects implementation |
None – to
be undertaken by the LGUs and the PMO starting 2007 |
|
Resources |
|
|
Costs |
|
Technical
assessment
On objectives
The Project objective in developing the
capabilities of the eligible LGUs was substantially achieved.
The Project accomplished 116 percent in terms of providing
capability building on project development to the LGUs and 156
percent in terms of number of participants. The post training
assessment of the participants for the resource speakers and the
training program as a whole were between very good to excellent.
The participants further confirmed the rating during the closing
programs when they rendered their impressions and insights.
On results
The capability
building program improved the capabilities of the LGUs in
preparing project proposals. The program has developed their
confidence in project development. Six out of the 37 recipient
LGUs prepared and submitted sub-project proposals to the PMO for
the ASSEF Project as of September 30, 2006.
On
assumptions/hypotheses
still valid
On
activities
Of the six
activities, only two activities were undertaken during the
period under review. The first activity – implementation of
project development training was substantially conducted by the PMO with 116% accomplishment in terms of target LGUs and 156% in
terms of target participants. For the second activity –
visualization of the preparation of micro project proposals, the
PMO received six micro project proposals from the participating
LGUs. The PMO conducted the initial evaluation of the
sub-project proposals and forwarded the evaluation reports to
the proponents. The PMO conducted technical assistance upon
request to the LGUs in the revision of the sub-project
proposals. The remaining activities will be undertaken starting
October 2006.
On expenses made
The expenses
made pertains to the purchase of supplies, reproduction of
handouts, meals and accommodation for the participants, gasoline
used for the transport of resource speakers and participants as
well as the honoraria of the resource persons for the capability
building training. It also includes the cost of laptop and
multi-media and the purchase of vehicle used during the last
batch of Capability Buiding Training and for monitoring of
sub-projects.
On the counterpart
The NEDA 5
provided counterpart to the Project during the period in the
amount of P 1,915,497.73 (see annex NEDA Counterpart to ASSEF