Organization
of Project Steering Committee (PSC) |
PSC organized |
|
|
|
|
|
|
|
|
|
|
|
|
AECI |
|
Organization
of Project Management Office (PMO) |
PMO organized |
|
|
|
|
|
|
|
|
|
|
|
|
NEDA 5 |
|
- Hiring
of two direct staffs (Technical Aide & Financial
Aide) |
2 Project Saff
hired |
|
|
|
|
|
|
|
|
|
|
|
|
AECI |
|
Release of
funds from the AECI |
Funds
deposited in ASSEF dollar account |
|
|
|
|
|
|
|
|
|
|
|
|
AECI |
|
Signing of MOA
between AECI and NEDA 5 |
Signed MOA
|
|
|
|
|
|
|
|
|
|
|
|
|
AECI & NEDA 5 |
|
Orientation of
PMO on ASSEF Project |
Project
understood by PMO |
|
|
|
|
|
|
|
|
|
|
|
|
NEDA 5 |
|
Finalization
of Project Documents |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
MOA format
between NEDA 5 & LGU |
Draft final
MOA format |
|
|
|
|
|
|
|
|
|
|
|
|
PMO |
|
Training
Design on Project Development |
Final Training
Design |
|
|
|
|
|
|
|
|
|
|
|
|
PMO |
|
2nd Draft
Templates for Sub-Projects |
Draft final
Templates |
|
|
|
|
|
|
|
|
|
|
|
|
PMO |
|
Orientation of
Target LGUs on ASSEF Project |
Project
understood by LGUs |
|
|
|
|
|
|
|
|
|
|
|
|
PMO |
|
Letter of Intent to
participate in the ASSEF Project |
Letter of
intent |
|
|
|
|
|
|
|
|
|
|
|
|
LGUs |
|
Implementation Phase |
|
Capability Building |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Organization of the
Training Teams |
Organized
Training Team |
|
|
|
|
|
|
|
|
|
|
|
|
PMO |
|
Orientation of the Training
Teams |
Assignments
accepted by the Training Team |
|
|
|
|
|
|
|
|
|
|
|
|
PMO |
|
Finalization
of the Training Module |
Final Training
Module |
|
|
|
|
|
|
|
|
|
|
|
|
Training
Team |
|
Finalization of Templates
for sub-projects |
Final
Templates for sub-projects |
|
|
|
|
|
|
|
|
|
|
|
|
Training
Team |
|
Reproduction of Hand-outs |
Handouts |
|
|
|
|
|
|
|
|
|
|
|
|
PMO |
|
Conduct of Training |
Enhanced
capabilities of LGUs on project development & draft
sub-project proposal |
|
|
|
|
|
|
|
|
|
|
|
|
Training
Team |
|
Preparation of
report on Capability Building |
Report on
Capability Building |
|
|
|
|
|
|
|
|
|
|
|
|
PMO |
|
Sub-Projects on Agriculture, Social & Environment |
|
Preparation of sub-project
proposal |
Sub-project
proposals |
|
|
|
|
|
|
|
|
|
|
|
|
LGUs |
|
Evaluation of sub-project
proposal |
Evaluation
reports |
|
|
|
|
|
|
|
|
|
|
|
|
PMO |
|
Finalization of sub-project
proposal |
Final
sub-project proposals |
|
|
|
|
|
|
|
|
|
|
|
|
LGUs |
|
Processing of requirements
for compliance by LGU |
Following
requirements for MOA signing completed by LGUs: |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
SB Resolution endorsing the
sub-project |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
SB Resolution allocation
local counterpart fund for the sub-project |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
SB Resolution authorizing
the Mayor to enter into MOA with NEDA 5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
SB Resolution adopting the
MOA |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
Bank Account of LGU for the
ASSEF Project- Machine validated bank certification of
local counterpart fund |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
Lot ownership
or lot donation(if necessary) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Organization
of the Implementing Unit |
Local
implementing unit organized |
|
|
|
|
|
|
|
|
|
|
|
|
LGUs |