Project Timeframe: April 2006-March 2009

 

ACTIVITIES EXPECTED OUTPUT
Particulars

2006

Unit(s)/Orgs
Responsible

1 2 3 4
J F M A M J J A S O N D
Pre-Implementation Phase
Organization of Project Steering Committee (PSC) PSC organized                        

AECI

Organization of Project Management Office (PMO) PMO organized                        

NEDA 5

 - Hiring of two direct staffs (Technical Aide & Financial Aide) 2 Project Saff hired                        

AECI

Release of funds from the AECI Funds deposited in ASSEF dollar account                        

AECI

Signing of MOA between AECI and NEDA 5 Signed MOA                        

AECI & NEDA 5

Orientation of PMO on ASSEF Project Project understood by PMO                        

NEDA 5

Finalization of Project Documents                          

 

MOA format between NEDA 5 & LGU Draft final MOA format                        

PMO

Training Design on Project Development Final Training Design                        

PMO

2nd Draft Templates for Sub-Projects Draft final Templates                        

PMO

Orientation of Target LGUs on ASSEF Project Project understood by LGUs                        

PMO

Letter of Intent to participate in the ASSEF Project Letter of intent                        

LGUs

Implementation Phase
Capability Building                            
Organization of the Training Teams Organized Training Team                        

PMO

Orientation of the Training Teams Assignments accepted by the Training Team                        

PMO

Finalization of the Training Module Final Training Module                        

Training
Team

Finalization of Templates for sub-projects Final Templates for sub-projects                        

Training
Team

Reproduction of Hand-outs Handouts                        

PMO

Conduct of Training Enhanced capabilities of LGUs on project development & draft sub-project proposal                        

Training
Team

Preparation of report on Capability Building Report on Capability Building                        

PMO

Sub-Projects on Agriculture, Social & Environment
Preparation of sub-project proposal Sub-project proposals                        

LGUs

Evaluation of sub-project proposal Evaluation reports                        

PMO

Finalization of sub-project proposal Final sub-project proposals                        

LGUs

Processing of requirements for compliance by LGU Following requirements for MOA signing completed by LGUs:                          
  SB Resolution endorsing the sub-project                        

 

  SB Resolution allocation local counterpart fund for the sub-project                        

 

  SB Resolution authorizing the Mayor to enter into MOA with NEDA 5                          
  SB Resolution adopting the MOA                          
  Bank Account of LGU for the ASSEF Project- Machine validated bank certification of local counterpart fund                          
  Lot ownership or lot donation(if necessary)                          
Organization of the Implementing Unit Local implementing unit organized                        

LGUs