MONITORING PROCEDURES
-
The PMCs must
have their respective monitoring plans prepared before the end
of the preceding year as the basis for their regular monitoring.
This plan should include specific projects as defined in Section
2.2 of this manual for each level of PMC. Regular updates of the
status of projects included in the monitoring plan should be
obtained from the implementing agencies and processed by the
PMCs.
-
From the list of projects to
be monitored for the current year, the PMC should be able to
schedule regular project field visits/inspections for a
particular reporting period. This schedule of project will now
be be included in the monitoring work program which the PMC will
fund and visit in a particular period. Detailed Programs of Work
(POW) on those projects to be visited must be secured prior to
the actual visit.
-
Conduct initial appraisal of
projects to be monitored based on information obtained from the
Monitoring Plan and the Initial Project Reports submitted by
project implementors. If the project is undertaken by contract,
secure if possible. Performance Bond and Notice to Proceed. If
undertaken by administration, check whether the required
"Authority to Undertake Project by Administration" has been
issued.
-
Coordinate/Establish linkage
with project implementors to ensure timely submission of
reports, accuracy of project evaluation and secure their
cooperation and active participation throughout the monitoring
process. Such coordination/linkage should include among others,
a briefing on the timing and scope of monitoring activities and
provision for a feedback mechanism on problems and issues
encountered during project implementation.
-
Analyze project/activity
accomplishment reports and project exception reports submitted
by project implementors and NGOs/POs respectively.
-
Conduct regular ocular
inspection at project sites on those projects which have been
programmed to be visited as well as those projects where
verification or validation of reports is needed due to the
magnitude of the delay. This activity will involve the
following:
-
Conduct interviews with
Project Engineer, laborers, barangay officials, and
reputable residents of the locality to validate status of
projects, reported problems/findings and to verify whether
the project is being implemented in accordance with approved
conditions, plans and specifications.
-
Compare reported
accomplishments against approved project schedules to
determine whether the project is behind or ahead of
schedule.
Examine accomplishment
chart/report or S-curve to detect slippage (difference
between targeted/programmed accomplishment and actual
accomplishment).
If the slippage is
positive, the project is ahead of schedule; if negative, it
is behind schedule.
Ascertain whether the
delay in project implementation is justifiable or not. some
causes of delay are:
-
lack of materials
-
liquidity problems of
contractor
-
delayed release of
funds
-
force majeure (natural
calamities)
-
right-of-way problem
-
peace and order
condition
-
Investigate any deviation
from the approved conditions, plans and specifications. Some
causes of deviation are:
-
modification/substitution of materials
-
increase in the
original quantities of any or all items of work
-
reclassification of an
existing item to another as provided for the original
contract
-
decrease in the
quantity of work due to under-runs or deletion of
portions or sections of the project
-
non-adherence of
contractor to the defined conditions in the contract
(e.g., maximum hiring of workers from the project site)
-
Determine whether
deviations are authorized or not, that is, they are covered
by a Change Order, Extra work Order or Suspension Order.
-
Assess quality of work
whether it is in accordance with established
engineering/quality control standards or within the level of
acceptability. Reference may be made to the results of the
Materials/Quality Control Testing conducted by authorized
personnel.
-
Obtain feedback from
laborers, local officials and concerned citizens to verify
reported anomalies/irregularities.
-
Report findings and
recommendations to the development councils or its ExCom for
deliberations/resolution/action. The ExCom or RDC meeting should
include a problem-solving item in its agenda. Problems and
issues that cannot be resolved at the local levels shall be
elevated to the next higher level or other appropriate bodies,
as the case may be.
-
Upon completion of the
project, conduct an evaluation of selected projects to determine
that the same is completed as per plans and specifications and
the targets are achieved. Verify Completion Report, Final
Inspection Reports and Certificate of Acceptance/Turn-over if
they are in order, Make an assessment of the lessons and
insights drawn in the course of project implementation and make
this available to project planners.