ANNEX B
|
PMC FORM O-1 |
|
PMC FORM O-2 |
|
PMC FORM O-3 |
|
PMC FORM O-4 |
Title: REPORT ON
STATUS OF PROJECTS ENCOUNTERING
PROBLEMS IN IMPLEMENTATION
(PMC FORM O-1)
Purpose: This
report will provide information on the various problems
encountered by on-going projects that impede their implementation.
Remedial measures to improve progress and other recommended courses
of action are likewise reflected in the report.
RESPONSIBILITY:
Project Monitoring committee
Municipal Level
Frequency:
To be prepared and submitted monthly
Distriution:
1 Copy - Municipal Development Council
1 Copy - Provincial Project Monitoring Committee
Submission
Date:
Municipal
Development Council - On the 7th day of the month
following the reference month
Provincial
Project Monitoring Committee (PMC) - Not later than two
(2) weeks after reference month
Regional Level
Frequency:
To be prepared and submitted quarterly
Distriution: 1 Copy - Regional Development Council (RDC)
1 Copy - NEDA Central Office
Submission
Date:
Regional Development Council (RDC) - On the
3rd week after reference quarter
President/Cabinet/NEDA Board - On or before the 3oth
day of the month after reference quarter
DEFINITION OF ENTRIES:
As of -
End of reporting period
Column (1)
Name of
Project -
Title of project encountering implementation problems
Column (2)
Location
- Region, province, city or municipality where project is
being implemented
Column (3)
Implementing Agency - Name of agency implementing the
program/project
Column (4)
Implementation Status (Target)
- Expected amount of work in
percent to be accomplished as of report date.
Column (5)
Implementation Status (Actual)
- Actual work accomplished as of
report date.
Column (6)
Slippage
- Difference between
actual (Column 5) and target (Column 4). It may be positive
(which means that the project is ahead of schedule),
negative (behind schedule) or zero (on schedule).
Column (7)
Issues
- Operational
constraints/concerns observe during project implementation
Column (8)
Source of
Information - Name of
agency/NGO/PVO or concerned citizens reporting the
problems/issues
Column (9)
Action
Taken/Recommendations
- Remedial measures taken/being
recommended to improve work progress or to commend
outstanding performance
At the end
of the report, indicate the NAME, DESIGNATION and OFFICE
of the person who accomplished the form and the DATE the report was
prepared.
PMC
FORM O-1
REPORT ON THE STATUS OF PROJECTS ENCOUTERING
PROBLEMS IN IMPLEMENTATION
As of ___________________________
|
Name of
Project/Program |
Location |
Implementing
Agency |
Implementation Status (%) |
Issues |
Source of
Information |
Action Taken/
Recommen-
dation |
|
Target |
Actual |
Slippage |
|
(1) |
(2) |
(3) |
(4) |
(5) |
(6) |
(7) |
(8) |
(9) |
| |
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
Prepared by:
_______________________
Office: ______________________
Designation : _______________________ Date
: ______________________
back to
top
Title: FINANCIAL AND
PHYSICAL STATUS OF CAPITAL INVESTMENT
PROGRAM/PROJECTS (PMC FORM O-2)
Purpose: This
report will provide information on the financial and physical
status of on-going capital investment programs/projects in a
specific area/location. It will contain the ts used to record the
basic information on capital investment programs/projects It will
contain the titles of on-going projects, implementing agency,
location, schedules (may be original or revised), the financial and
physical performance of each project and problems encountered in
implementation.
RESPONSIBILITY:
Project Monitoring Committee
Municipal Level
FREQUENCY: To be
prepared and submitted monthly
DISTRIBUTION:
1 Copy - Municipal Development Council
1 Copy - Provincial Project Monitoring Committee
SUBMISSION
DATE:
Municipal
Development Council - On the 7th day of the month
following the reference month
Provincial
Project Monitoring Committee - Not later than two (2)
weeks after reference month.
Provincial Level
FREQUENCY: To be
prepared and submitted monthly to the Provincial/City
Development Council; quarterly to the regional Project
Monitoring Committee (RPMC)
DISTRIBUTION:
1 Copy - Provincial/City Development Council
1 Copy - Regional Project Monitoring Committee
SUBMISSION
DATE:
Provincial/City Development Council - On the 7th day of
the month following the reference month
Regional
Project Monitoring Committee - Not later than two (2)
weeks after reference month.
Regional Level
FREQUENCY: To be
prepared and submitted quarterly
DISTRIBUTION:
1 Copy - Regional Development Council
1 Copy - NEDA Central Office
SUBMISSION
DATE:
Regional
Development Council - On the 3rd week after reference
quarter
President/Cabinet/NEDA Board - On or before the 30th day
of the month after reference quarter
DEFINITION OF
ENTRIES:
As of - End of reporting period
Region/Province/City/Municipality - Area or level where projects
are being implemented
Column (1)
Project Title - Title of project as found in approved
program of work
Agency - Name of agency implementing the project (IA, GOCCs,
LGUs)
Location - Exact location of the project
Column (2)
Schedule
(Start/Completion Dates) - Date when the project started
and will be completed in month, day and year
FINANCIAL
STATUS (Php '000)
Column (3)
Program -
Total amount of funds required from the start of project
implementation to reporting date, based on the approved
program of work
Column (4)
AA Issued -
Cumulative total Advices of Allotment issued by DBM to the
program/project from start of implementation to reporting
date, based on the approved program of work
Column (5)
Funding Support
- Total AA issued (Column 4) divided by Program (Column
3)
Column (6)
Expenditure
(Unpaid Obligation) - Accounts committed to be paid for
servies rendered and/or work accomplished as of report date
Column (7)
Expenditure
(Disbursement) - Actual cash payments made though the
issuance of Treasury Warrants and/or checks to the project
as of report date
Column (8)
Expenditure
(Total) - Sum of unpaid obligation (Column 6) and
disbursement (Column 7)
Column (9)
Expenditure
Rate - Total expenditure (Column 8) divided by Program
(Column 3), multiplied by 100
PHYSICAL
STATUS
Column (10)
Target -
Expected amount of work to be accomplished in percentage
from the start of project implementation up to the report
date.
Column (11)
Actual -
Actual work accomplished in terms of percentage to total
target of the whole project from start of implementation up
to report period
Column (12)
Slippage -
Difference between Actual (Column 11) and Physical Target
(Column 10). It may be positive (which means that the
project is ahead of schedule), negative (behind schedule),
or zero (on schedule).
Column (13)
Performance
- Actual physical (Column 11) divided by target (Column 10)
multiplied by 100.
Column (14)
Employment
Generated - Employment generated by the project in
man-days
Column (15)
Remarks -
Additional information on the project, such as problems
encountered that impede project implementation, remedial
measures taken, etc.
At the end of
report, indicate the NAME, DESIGNATION and OFFICE of the person who prepared the report and the
DATE the
report was prepared.
PMC
FORM O-2
FINANCIAL AND PHYSICAL STATUS OF
CAPITAL INVESTMENT PROGRAMS/PROJECTS
As of: _________________________________________
a) Project Title
b) Agency
c) Location |
Schedule
a) Start
b) Com-pletion Date |
FINANCIAL (Php '000) |
PHYSICAL (%) |
Employ-
ment
Gene-
rated
(Man-
Days) |
Remarks |
|
Pro-grams |
AA
Issued
to Date |
Funding
Support
(%) |
EXPENDITURE |
Expen-
diture
Rate
(%) |
Target |
Actual |
Slip-page |
Perfor-
mance |
|
Unpaid
Obli-gation |
Disburse-
ment |
Total |
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Prepared by:
_______________________
Office: _______________________
Designation : _______________________ Date:
_______________________
back to
top
Title: SUMMARY OF FINANCIAL
AND PHYSICAL ACCOMPLISHMENT
BY AGENCY (PMC FORM O-3)
Purpose: This
report will provide a summary of the financial and physical
accomplishment broken down by implementing agency. It will
contain information on the number of projects and the overall
financial and physical status of projects being implemented by each
agency in the region, province/city or municipality. This report
will likewise contain the overall performance for the area.
RESPONSIBILITY:
Project Monitoring Committee
Municipal Level
FREQUENCY: To be
prepared and submitted monthly
DISTRIBUTION:
1 Copy - Municipal Development Council
1 Copy - Provincial Project Monitoring Committee
SUBMISSION
DATE:
Municipal
Development Council - On the 7th day of the month
following the reference month
Provincial
Project Monitoring Committee - Not later than two (2)
weeks after reference month.
Provincial Level
FREQUENCY: To be
prepared and submitted monthly to the Provincial/City
Development Council; quarterly to the regional Project
Monitoring Committee (RPMC)
DISTRIBUTION:
1 Copy - Provincial/City Development Council
1 Copy - Regional Project Monitoring Committee
SUBMISSION
DATE:
Provincial/City Development Council - On the 7th day of
the month following the reference month
Regional
Project Monitoring Committee - Not later than two (2)
weeks after reference month.
Regional Level
FREQUENCY: To be
prepared and submitted quarterly
DISTRIBUTION:
1 Copy - Regional Development Council
1 Copy - NEDA Central Office
SUBMISSION
DATE:
Regional
Development Council - On the 3rd week after reference
quarter
President/Cabinet/NEDA Board - On or before the 30th day
of the month after reference quarter
DEFINITION OF
ENTRIES:
As of - End of reporting period
Region/Province/City/Municipality - Specific area where projects
are being implemented
Column (1)
Agency -
Name of agency implementing agency
Column (2)
Number of
Projects - Total number of projects being implemented by
the agency in the specified area
FINANCIAL
STATUS (Php '000)
Column (3)
Program -
Total amount of funds required by the agency to accomplish
targets from start of project to reporting period
Column (4)
AA Issued -
Cumulative total Advices of Allotment issued by DBM to the
agency from start of implementation to reporting date
Column (5)
Funding Support
- Total AA issued (Column 4) divided by Program (Column
3)
Column (6)
Expenditure
(Unpaid Obligation) - Accounts committed to be paid for
services rendered and/or work accomplished by each agency as
of reporting date
Column (7)
Expenditure
(Disbursement) - Total actual cash payments made by each
agency though the issuance of Treasury Warrants and/or
checks as of reporting date
Column (8)
Expenditure
(Total) - Sum of unpaid obligation (Column 6) and
disbursement (Column 7) for each agency
Column (9)
Expenditure
Rate - Total expenditure (Column 8) divided by Program
(Column 3), multiplied by 100
PHYSICAL
STATUS
Column (10)
Target -
Expected overall amount of work (in percentage) to be
accomplished by each agency as of report date. Overall
agency weighted target
Column (11)
Actual -
Actual work accomplished by each agency (in percentage) as
of reporting date. Overall agency weighted accomplishment
Column (12)
Slippage -
Difference between Actual (Column 11) and Target (Column
10). It may be positive (which means that the project is
ahead of schedule), negative (behind schedule), or zero (on
schedule).
Column (13)
Performance
- Actual (Column 11) divided by target (Column 10)
multiplied by 100.
Column (14)
Employment
Generated - Employment generated by the on-going
projects of the agency expressed in man-days
Column (15)
Remarks -
Additional information on the project, such as problems that
impede project implementation, remedial measures taken, etc.
At the end of
report, indicate the NAME, DESIGNATION and OFFICE of the person who prepared the report and the
DATE the
report was prepared.
PMC
FORM O-3
SUMMARYOF FINANCIAL AND PHYSICAL ACCOMPLISHMENT BY AGENCY
As of: _________________________________________
Region/Province/Municipality: ______________________
|
Agency |
Number of Projects |
FINANCIAL (Php '000) |
PHYSICAL (%) |
Employ-
ment
Gene-
rated
(Man-
Days) |
Remarks |
|
Pro-grams |
AA
Issued
to Date |
Funding
Support
(%) |
EXPENDITURE |
Expen-
diture
Rate
(%) |
Target |
Actual |
Slip-page |
Perfor-
mance |
|
Unpaid
Obli-gation |
Disburse-
ment |
Total |
|
(1) |
(2) |
(3) |
(4) |
(5) = (4)/(3) x 100 |
(6) |
(7) |
(8) = (6) + (7) |
(9) = (8)/(3) x 100 |
(10) |
(11) |
(12)= (11) - (10) |
(13) = (11)/(10) x 100 |
(14) |
(15) |
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Overall
>> |
Prepared by:
_______________________
Office: _______________________
Designation : _______________________ Date:
_______________________
back to
top
Title: SUMMARY OF FINANCIAL
AND PHYSICAL ACCOMPLISHMENT
BY SECTOR (PMC FORM O-4)
Purpose: This
report will provide a summary of the financial and physical
accomplishment by sector. It will contain information on the number
of on-going projects and the overall financial and physical
performance of the projects being implemented by each sector in the
specific areas (region, province, city or municipality). This report
will likewise contain the overall performance of projects
implemented in the area.
RESPONSIBILITY:
Project Monitoring Committee
Municipal Level
FREQUENCY: To be
prepared and submitted monthly
DISTRIBUTION:
1 Copy - Municipal Development Council
1 Copy - Provincial Project Monitoring Committee
SUBMISSION
DATE:
Municipal
Development Council - On the 7th day of the month
following the reference month
Provincial
Project Monitoring Committee - Not later than two (2)
weeks after reference month.
Provincial Level
FREQUENCY: To be
prepared and submitted monthly to the Provincial/City
Development Council; quarterly to the regional Project
Monitoring Committee (RPMC)
DISTRIBUTION:
1 Copy - Provincial/City Development Council
1 Copy - Regional Project Monitoring Committee
SUBMISSION
DATE:
Provincial/City Development Council - On the 7th day of
the month following the reference month
Regional
Project Monitoring Committee - Not later than two (2)
weeks after reference month.
Regional Level
FREQUENCY: To be
prepared and submitted quarterly
DISTRIBUTION:
1 Copy - Regional Development Council
1 Copy - NEDA Central Office
SUBMISSION
DATE:
Regional
Development Council - On the 3rd week after reference
quarter
President/Cabinet/NEDA Board - On or before the 30th day
of the month after reference quarter
DEFINITION OF
ENTRIES:
As of - End of reporting period
Region/Province/City/Municipality - Specific area where projects
are being implemented
Column (1)
Sector -
Sector or category of projects
Column (2)
Number of
Projects - Total number of projects being implemented
under the sector in the specified area
FINANCIAL
STATUS (Php '000)
Column (3)
Program -
Total amount of funds required by the sector to accomplish
targets from start of project to reporting period
Column (4)
AA Issued -
Cumulative total Advices of Allotment issued by DBM to the
agency from start of implementation to reporting date
Column (5)
Funding Support
- Total AA issued (Column 4) divided by Program (Column
3)
Column (6)
Expenditure
(Unpaid Obligation) - Total accounts committed to be
paid for services rendered and/or work accomplished by each
sector as of reporting date
Column (7)
Expenditure
(Disbursement) - Total actual cash payments made by each
sector though the issuance of Treasury Warrants and/or
checks as of reporting date
Column (8)
Expenditure
(Total) - Sum of unpaid obligation (Column 6) and
disbursement (Column 7) for each sector
Column (9)
Expenditure
Rate - Total expenditure (Column 8) divided by Program
(Column 3), multiplied by 100
PHYSICAL
STATUS
Column (10)
Target -
Expected overall amount of work (in percentage) to be
accomplished by each sector as of reporting period (weighted
sectoral target in percent)
Column (11)
Actual -
Actual work accomplished by each sector (in percentage) as
of reporting period (weighted sectoral accomplishment in
percent)
Column (12)
Slippage -
Difference between Actual (Column 11) and Target (Column 10)
physical accomplishment by each sector. It may be positive
(which means that the project is ahead of schedule),
negative (behind schedule), or zero (on schedule).
Column (13)
Performance
- Actual (Column 11) divided by target (Column 10)
multiplied by 100.
Column (14)
Employment
Generated - Employment generated by the sector expressed
in man-days
Column (15)
Remarks -
Additional information on the project, such as problems that
impede project implementation, remedial measures taken, etc.
At the end of
report, indicate the NAME, DESIGNATION and OFFICE of the person who prepared the report and the
DATE the
report was prepared.
PMC
FORM O-4
SUMMARYOF FINANCIAL AND PHYSICAL ACCOMPLISHMENT BY SECTOR
As of: _________________________________________
Region/Province/Municipality: ______________________
|
Sector |
Number of Projects |
FINANCIAL (Php '000) |
PHYSICAL (%) |
Employ-
ment
Gene-
rated
(Man-
Days) |
Remarks |
|
Pro-grams |
AA
Issued
to Date |
Funding
Support
(%) |
EXPENDITURE |
Expen-
diture
Rate
(%) |
Target |
Actual |
Slip-page |
Perfor-
mance |
|
Unpaid
Obli-gation |
Disburse-
ment |
Total |
|
(1) |
(2) |
(3) |
(4) |
(5) = (4)/(3) x 100 |
(6) |
(7) |
(8) = (6) + (7) |
(9) = (8)/(3) x 100 |
(10) |
(11) |
(12)= (11) - (10) |
(13) = (11)/(10) x 100 |
(14) |
(15) |
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Overall
>> |
Prepared by:
_______________________
Office: _______________________
Designation : _______________________ Date:
_______________________