ANNEX A
|
PMC FORM I-1 |
|
PMC FORM I-2 |
|
PMC FORM I-3 |
Title: INITIAL
PROJECT REPORT (PMC FORM I-1) PHYSICAL AND FINANCIAL TARGETS
FOR CAPITAL INVESTMENT PROGRAMS/PROJECTS
Purpose: This
report is used to record the basic information on capital
investment programs/projects that are being implemented by the
agency, GOCC or LGU. It will contain such information as name of
project, funding source, location, total projecr cost, project
schedule, mode of implementation and the physical and financial
targets for the year.
RESPONSIBILITY:
Implementing Agencies/GOCCS/LGUs
FREQUENCY: To be
submitted at the beginning of the year or at the start of the
project and updated annually for multi year projects
SUBMISSION DATE:
After the project has been bidded or awarded/contracted out or at
the start of the project.
DISTRIBUTION:
1 copy - Project Monitoring Committee
IMPLEMENTOR:
Name of Agency/GOCC/LGU that implements the project .
For
Column (1), indicate the following:
(A) Name of
Project - Title of project as found in the approved program
of work, loan or grant agreement. For reporting of subprojects
(i.e., contracts, components) indicate reference to mother
project title
(B) Location
- Barangay/municipality/city/province/region where project is
implemented
(C)
Sector-Sub-sector - Refers to the sector and sub-sector of
the project (e.g., infrastructure - roads; social development -
education; agriculture - crops, etc) refer to Annex C for
sector/sub-sector listing
(D) Funding
Source - Indicate source of fund for the project, whether:
Internal Revenue Allotment Share, , Calamity Fund, National
Government Appropriations, Corporate Funds of GOCCs, Foreign
Assisted Loan or Grant (e.g., ADB, WB, OECP, JICA, etc.)
(E) Force
Account/Pakyaw/Name of Contractor - Indicate whether project
work will be implemented by force account, pakyaw or if by
contract, state name of contractor
(F) Project
Schedule (Start/End) - Month, day and year the project is
expected to start and to be completed
Columns (3-14) - Correspond to the physical and financial
targets for the twelve (12) months of the year. For these columns,
indicate the following:
Financial
Schedule (Php '000) - Amount programmed for activities
scheduled for implementation for the month;
Physical
Targets in Percent (%) - Equivalent target in percent (as a
percentage of total project) for implementation for the month;
Output
Indicator/Targets - Indicate selected major
activities/milestone (at most 5) where accomplishment is to be
measured expressed in terms of physical units (e.g., hectares to
be irrigated, number of classrooms to be constructed, kilometers
of roads to be constructed, trainings to be conducted, children
to vaccinated, etc.) with corresponding targets for the month;
and
Employment
Generated (in man-days) - Employment targeted to be
generated by the project, expressed in man-days for the month.
Columns
15 (Total) - Represents the total targets (sum of column 3-14)
for the calendar year.
At the end of
report, indicate the NAME, DESIGNATION and OFFICE
of the person who prepared the report and the DATE the
report was prepared. Said report should be noted by the Head of
Agency at that given level.
PMC
FORM I-1
INITIAL PROJECT REPORT
Physical and Financial Targets for Capital Investment
Programs/Projects
Implementors : _________________________________________
(A)
Name of Project
(B) Location
(C) Sector/Sub-Sector
(D) Funding Source
(E) Force Account/Pakyaw/Name of
Contractor
(F) Project Schedule |
Total
Project
Cost
(2) |
CY _____
PHYSICAL/FINANCIAL TARGET |
Jan
(3) |
Feb
(4) |
Mar
(5) |
Apr
(6) |
May
(7) |
June
(8) |
July
(9) |
Aug
(10) |
Sept
(11) |
Oct
(12) |
Nov
(13) |
Dec
(14) |
Total
(15) |
| 1.
|
FS
%
OI
EG |
|
|
|
|
|
|
|
|
|
|
|
|
|
| 2.
|
FS
%
OI
EG |
|
|
|
|
|
|
|
|
|
|
|
|
|
| 3.
|
FS
%
OI
EG |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
FS -
Financial Schedule % - Overall Physical Target in
Percent OI - Output Indicator/Target EG -
Employment Generated |
Prepared by:
_______________________
Designation : _______________________
Noted: ____________________
Date:
_______________________
Agency Head
back to
top
Title: PHYSICAL AND
FINANCIAL ACCOMPLISHMENT REPORT
FOR CAPITAL
INVESTMENT PROGRAMS/PROJECTS
(PMC FORM I-2)
Purpose: This
report will provide information on the status of implementation
of projects in the specific areas on a monthly basis. It involves
reporting on the status of the overall accomplishment and financial
status for the month and as of reporting period. Also reflected in
the report are the problems encountered by the implementing agency
that impede project implementation.
RESPONSIBILITY:
Implementing Agencies/GOCCS/LGUs
FREQUENCY: To be
submitted monthly
SUBMISSION DATE:
Municipal/City/Provincial Level
On or before the
30th day of the month under report
Regional
Level
Not later than
two (2) weeks after reference quarter
DISTRIBUTION:
1 copy - Project Monitoring Committee
DEFINITION OF
ENTRIS:
As of
- refers to the reference month
Implementor - Name of implementing agency, GOCC or LGU
implementing the projects
Region - Region where projects are being implemented
Province/City - Province or city where projects are being
implemented
Column
(1)
Name of Project -
Title of project as found in the approved program of work
Date Started -
Month, day and year when project actually started
Target Completion
Date - Date when the project is scheduled to be completed
Column
(2)
Location -
Municipality/City where project is being implemented
(Columns
3-6) FINANCIAL STATUS (Php '000)
Column (3)
-
Program
(Calendar Year) - Cumulative total amount of funds
required during the year based on the approved program
of work
-
AA issued (Calendar
Year) - Cumulative total Advices of Allotment (issued by DBM to the project firm from start of the calendar year)
Column (4)
-
Program to Date -
Cumulative amount of funds required from start of
project to reporting date based on the approved program
of work (covers annual and multi year projects)
-
AA Issued to Date -
Cumulative total Advices of Allotment issued by DBM from
start of the project to reporting date
Column (5)
Expenditure (Unpaid
Obligation to Date) - Total accounts committed to be paid
for services rendered and/or work accomplished
Column (6)
Expenditure
(Disbursement to Date) - Actual cash payments made through
the issuance of Treasury Warrants and/or checks to the
project, cumulative from the start of project implementation
up to reporting date
Column (7 - 9)
PHYSICAL STATUS (%)
Column (7)
Output
Indicator - Refers to project activities/milestones
where accomplishment is to be measured. Output indicator no.
1 should reflect overall project target and accomplishment
in percentage from start of the project to reporting period
with succeeding output indicators to indicate selected major
indicators and their corresponding targets and
accomplishments.
Column (8)
Target to
Date - Work scheduled to be accomplished from start of
project implementation up to the reporting period.
Column (9)
Actual
this Month - Actual work accomplished from start of
implementation up to the reporting period.
Column (10)
Actual to
Date - Actual work accomplished from start of
implementation up to the reporting period.
Column (11)
Employment
Generated - Employment generated by the project from
start of the project to reporting period expressed in terms
of man-days.
Column (12)
Remarks
- Additional information on the project, such as problems
encountered that impede project implementation, remedial
measures taken, etc.
At the end
of the report, indicate the NAME, DESIGNATION and OFFICE
of the person who accomplished the form and the DATE the report was
prepared. Said report should be noted by the HEAD OF AGENCY
at the particular level.
PMC
FORM I-2
PHYSICAL AND FINANCIAL ACCOMPLISHMENT REPORT
for Capital Investment
Programs/Projects
As of ________________________________________________
Implementors : _______________________________________
region :
_______________________________________
PROVINCE:
_______________________________________
|
a) Name of
Proect
b) Date Started
c) Target Completion Date
|
Location
(City/
Muni-
pality)
|
FINANCIAL STATUS (%) |
PHYSICAL STATUS |
EMPLOYMENT
GENERATED
To Date
(Man-Days) |
REMARKS
1) Prob-lems/Issues of
imple-mentation
2) Recom-
mendation
|
|
a) Pro-gram
b) AA Issued CY __ |
a) Pro-gram
b) AA Issued To Date |
EXPENDITURE |
Output
Indicator |
Target
to
Date |
Actual
This
Month |
Actual
To
Date |
Unpaid Obligations
To Date |
Disbursement
To Date |
|
(1) |
(2) |
(3) |
(4) |
(5) |
(6) |
(7) |
(8) |
(9) |
(10) |
(11) |
(12) |
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
Prepared by:
_______________________
Designation : _______________________
Noted: ____________________
Date:
_______________________
Agency Head
back to
top
Title: PROJECT
EXCEPTION REPORT (PMC FORM I-3)
Purpose: This
report is used when implementation
problems needing immediate action by the Project Monitoring
Committee/Development Councils are encountered or when project
implementation has been outstanding. It records the critical
problems that would result in delays in project implementation
outside the tolerable limits, in the case of the former, and the
factors that contribute to outstanding performance in the case of
the latter.
RESPONSIBILITY:
Non-Government Organizations, Concerned Citizens and Agencies
FREQUENCY: To be
submitted as the need arises
DISTRIBUTION:
1 Copy - Project Monitoring Committee
DEFINITION OF
ENTRIES:
Name of
Project - Title of Project as found in the approved program
of work
Sector/Sub-Sector - Sector or sub-sector to which the
project falls (Refer to Annex C for Listings)
Location -
Municipality/City/Province/Region where project is being
implemented
Implementing
Agency - Name of agency implementing the project
Implementing
Status - Physical accomplishment of the project and indicate
whether the project is ahead of schedule, behind schedule, or on
schedule. Mark appropriate status.
Findings -
Problems encountered in project implementation or outstanding
performance of a project.
Possible
Reasons/Causes - Events, incidents, etc. that may have
caused the problems (e.g., delayed release of funds,
contractors' poor performance) or factors that contribute to the
outstanding performance.
Recommendations - Suggestions to improve work progress or to
commend outstanding performance.
At the end
of the report, indicate the NAME, DESIGNATION and OFFICE
of the person who accomplished the form and the DATE the report was
prepared. Said report should be noted by the HEAD OF AGENCY
at the particular level.
PMC
FORM I-3
PROJECT EXCEPTION REPORT
Name of
Project: _______________________
Location: _______________________________
Sector/Subsector: ______________________
Implementing Agency: _____________________
Implementation Status:
( ) Ahead ( )
Behind Schedule
( ) On Schedule
|
FINDINGS |
POSSIBLE
REASONS/CAUSES |
RECOMMENDATIONS |
| |
|
|
| |
|
|
| |
|
|
Prepared by:
_______________________
Office: ______________________
Designation : _______________________ Date
: ______________________