Name of Bridge/
Station |
Road Section/
Location |
Proposed Type/
Length (LM) |
Project
Cost (PM) |
Date
a. Start
b. Target
c. Revised |
Percent
Accomplish-
ment |
Remarks |
Bayabas
Km. 276+042 |
Manila South Road, Labo, CNorte |
40 |
16.00 |
a 1/00/06
b 7/00/06
|
|
Scheduled for bidding on Jan. 5, 2006 |
Hibago
Km. 446+800 |
Anayan-Ocampo-Balangao-Tigaon Rd., CSur |
55 |
19.80 |
a
8/26/05
b 3/13/06 |
45.40 |
On-going with 9.74% slippage |
Malatap
Km. 297+428 |
Manila South Road, Labo, CNorte |
40 |
16.00 |
a
7/00/07
b 12/00/07 |
|
Not Yet Started |
Naboangan
Km. 310+432 |
Manila South Road, Labo, CNorte |
40 |
16.00 |
a
7/00/97
b 12/00/07 |
|
Not Yet Started |
Kanapawan
Km. 289+980
|
Manila South Road, Labo, CNorte |
55 |
22.00 |
a
7/00/07
b 12/00/07 |
|
Not Yet Started |
Macogon
Km. 302+517 |
Manila South Road, Labo, CNorte |
45 |
18.00 |
a
7/00/07
b 12/00/07 |
|
Not Yet Started |
Balabagon
Km. 576+517 |
Manila South Road, Labo, CNorte |
40 |
16.00 |
a
7/00/07
b 12/00/07 |
|
Not Yet Started |
Teres (Phase1)
Km. 543+400 |
Teres-Garchitorena Road, CSur |
90 |
7.73 |
a
1/31/04
b 3/13/06 |
87.77 |
Suspended |
|
Teres (Phase II) |
Teres-Garchitorena Road, CSur |
|
4.17 |
a
4/10/04
|
52.21 |
Suspended |
|
Teres (Phase II) |
Teres-Garchitorena Road, CSur |
|
9.07 |
a
1/21/04 |
53.43 |
Suspended |
Daguit Phase II
Km. 306+224 |
Manila South Road, Labo, CNorte |
50 |
20.00 |
a
7/00/07
b 12/00/07 |
|
Not Yet Started |
Maangas
Km. 516+700 |
Lagonoy-Presentacion Road, CSur |
60 |
8.38 |
a
6/00/04 |
82.00 |
Suspended |
Tilod
Km. 923+030 |
Jct. Bato-Baras Rd, Catanduanes |
40 |
16.00 |
a 7/00/07
b 12/00/07 |
|
Not Yet Started |
Salvacion Phase I
Km. 276+042 |
Lagonoy-San Vicente-Caramoan-Guijalo Rd., CSur |
60 |
7.55 |
c
6/30/05 |
100 |
Completed |
|
Salvacion Phase II |
Lagonoy-San Vicente-Caramoan-Guijalo Rd., CSur |
|
4.24 |
c
8/28/05 |
100 |
Completed |
|
Salvacion Phase III |
Lagonoy-San Vicente-Caramoan-Guijalo Rd., CSur |
|
7.42 |
a
6/21/04 |
92.00 |
Suspended |