PROCEDURES
FOR COMPUTING ACCOMPLISHMENTS
Financial Accomplishment
Funding Support
-
Get the sum of releases
-
Compute for the
total programmed amount
-
Divide total releases by total programmed amount and
multiply by 100 to get financial support (%).
Financial Support (%) =
Total Releases
x 100
Total Programmed Amount
Expenditure Rate (%)
-
Get the sum of
expenditures by adding unpaid obligation and cash
disbursement
-
Compute for the
total programmed amount
-
Divide total
expenditures by total programmed amount and multiply by 100
to get expenditure rate (%).
Expenditure Rate (%) =
Total Expenditures
x 100
Total Programmed Amount
Physical Accomplishment
-
Identify the components of the project
and its costs.
-
Compute for the relative weight of each
component by taking the ratio of the cost of each component
to the total project cost.
-
Compute for cumulative percent
accomplishment (target and actual) of each component by
taking the ratios of the target and actual accomplishment to
the total component target.
-
Multiply the percent accomplishment by
the relative weight of the project component to get the
weighted accomplishment of each component.
-
Add up the weighted accomplishment of
each project component to get the overall weighted project
accomplishments.
-
Subtract target accomplishment from
actual accomplishment to get project component slippage.
Mathematical Format for Computing Project Accomplishment
Project
Component
|
Cost
|
Relative
Weight |
ACCOMPLISHMENT (%) |
WEIGHTED |
Slippage |
|
Target |
Actual |
Target |
Actual |
|
(1) |
(2) |
(3) |
(4) |
(5) |
(6) |
(7) |
(8) - (5) - (4) |
|
PC1 |
c1 |
w1 = c1
ct |
t1 |
a1 |
w1 x t1 |
w1 x a1 |
S1 |
|
PC2 |
c2 |
w2 = c2
ct |
t2 |
a2 |
w2 x t2 |
w2 x a2 |
S2 |
|
PCn |
cn |
wn = cn
ct |
tn |
an |
wn x tn |
wn x an |
Sn |
|
n
n
n
n
n
Σ ci = ct Σ
ci/ct = Σ wi=1.0
Σ wi x ti = A
Σ wi x ai = B
i = 1
i=1 i=1
i=1
i=1 |
OVERALL WEIGHTED PERFORMANCE =
B x 100 =
(percent)
A
OVERALL PROJECT SLIPPAGE = B - A = (percent)
Where:
i = 1,2,3,........ n
(as component of project)
t = target in terms of equivalent percent for each component of
project
a = actual accomplishment in equivalent percent for each
component of project
w = relative weight of a component to total project based on
cost
c = cost of each component
s = slippage difference between actual and scheduled
accomplishment
A = overall weighted project target in percent
B = overall weighted project accomplishment in percent
PHYSICAL
ACCOMPLISHMENT OF AGENCY
-
Identify all on-going
projects of the agency and their costs.
-
Compute for he
relative weight of each project taking the ratio of the cost of
each project to the total cost of all projects of the agency
scheduled for the year.
-
Compute s for the
cumulative percent accomplishment (target and actual) of each
project by taking the the ratios of the target and actual
accomplishment of each project.
-
Multiply the percent
accomplishment by the relative weight of the project to get the
weighted accomplishment of each project.
-
Add up the weighted
accomplishment of each project to get the overall weighted
agency accomplishments.
-
Subtract target
accomplishment from actual accomplishment to get project
slippage.
Mathematical Format for
Agency Accomplishment
Project
|
Cost
|
Relative
Weight |
ACCOMPLISHMENT (%) |
WEIGHTED |
Slippage |
|
Target |
Actual |
Target |
Actual |
|
(1) |
(2) |
(3) |
(4) |
(5) |
(6) |
(7) |
(8) - (5) - (4) |
|
PC1 |
C1 |
W1 |
T1 |
A1 |
W1 x T1 |
W1 x A1 |
S1 |
|
PC2 |
C2 |
W2 |
T2 |
A2 |
W2 x T2 |
W2 x A2 |
S2 |
|
PCn |
Cn |
Wn |
Tn |
An |
Wn x Tn |
Wn x An |
Sn |
|
WT
n
n
n
n
Σ Ci = Ct Σ
Ci/Ct = WT = 1.0
Σ Wi x Ti = AT
Σ Wi x Ai = BT
i = 1 i=1 i=1 i=1 |
OVERALL WEIGHTED PERFORMANCE =
BT x 100 =
(percent)
AT
OVERALL PROJECT SLIPPAGE = BT - AT = (percent)
Where:
i = 1,2,3,........ n
(as component of project)
C = cost of each project
W = relative weight of project to total agency projects based on
cost
T = target of project in equivalent percent
A = actual accomplishment of project in equivalent percent
S = slippage of project or difference between actual and scheduled
accomplishment
AT = overall weighted agency target in percent
BT = overall weighted agency accomplishment in percent
PHYSICAL
ACCOMPLISHMENT OF AREA COVERED
-
Identify the
agencies implementing projects in the region, province, city or
municipality and compute for the total cost of all projects
scheduled for implementation during the year per agency.
-
Compute for
relative weight of each agency to total cost (area) by taking
the ratio of total cost of each agency's projects to total cost
of all projects in the area.
-
Compute for the
cumulative percent accomplishment (target and actual) of each
agency by taking the ratios of the target and actual
accomplishment to the total agency target.
-
Multiply percent
accomplishment of each agency by the relative weight of the
agency to get the weighted accomplishment of each agency.
-
Add up the
weighted accomplishment of each agency to get the overall
weighted area accomplishment.
-
Subtract target
accomplishment from actual accomplishment to get project
slippage.
Mathematical Format for
Area Accomplishment
|
Agency |
Cost |
Relative
Weight |
ACCOMPLISHMENT (%) |
WEIGHTED |
Slippage |
|
Target |
Actual |
Target |
Actual |
|
(1) |
(2) |
(3) |
(4) |
(5) |
(6) |
(7) |
(8) - (5) - (4) |
|
AGENCY1 |
C1 |
W1 |
T1 |
A1 |
W1 x T1 |
W1 x A1 |
S1 |
|
AGENCY2 |
C2 |
W2 |
T2 |
A2 |
W2 x T2 |
W2 x A2 |
S2 |
|
AGENCYn |
Cn |
Wn |
Tn |
An |
Wn x Tn |
Wn x An |
Sn |
|
CT
WT
AT
BT
n
n
n
n
Σ Ci = Ct Σ
Wi = WT = 1.0
Σ Wi x Ti = AT
Σ Wi x Ai = BT
i = 1 i=1 i=1 i=1 |
OVERALL WEIGHTED PERFORMANCE =
BT x 100 =
(percent)
AT
OVERALL PROJECT SLIPPAGE = BT - AT = (percent)
Where:
i = 1,2,3,........ n
(as component of project)
C = cost of each project
W = relative weight of project to total agency projects based on
cost
T = target of project in equivalent percent
A = actual accomplishment of project in equivalent percent
S = slippage of project or difference between actual and scheduled
accomplishment
AT = overall weighted agency target in percent
BT = overall weighted agency accomplishment in percent
SAMPLE CASE FOR COMPUTING PERFORMANCE AND SLIPPAGE
-
Compute for the
relative weight of each project component/project/agency.
Component
Project/Agency |
Cost
(in Php 000) |
Relative Weight |
|
A |
500 |
500/100 = 0.5 |
|
B |
300 |
300/100 = 0.3 |
|
C |
200 |
200/100 = 0.2 |
|
TOTAL |
100 |
1.0 |
- Compute for the percent accomplishment (performance) as of
reporting period.
Component/
Project |
Overall
Target
(Whole Year) |
Accomplishment |
Percent
Accomplishment |
|
Schedule |
Actual |
Schedule |
Actual |
|
A |
6 km. |
6 km. |
2 km. |
3/6 x
100 = 50% |
2/6 x
100 = 33% |
|
B |
3 km. |
2 km. |
1 km. |
2/3 x
100 - 66% |
1/3 x
100 = 33% |
|
C |
1 ha. |
1 ha. |
1 ha. |
1/1 x
100 = 100% |
1/1 x
100 = 100% |
- Compute for the weighted project performance
Component/
Project |
Overall
Target
(Whole Year) |
Percent
Accomplishment |
Weighted
Accomplishment |
|
Schedule |
Actual |
Schedule |
Actual |
|
A |
0.5 |
50 |
33 |
50 (.5)
= 25.0 |
33 (.5)
= 16.50 |
|
B |
0.3 |
66 |
33 |
66 (.3)
= 19.80 |
33 (.3)
= 9.90 |
|
C |
0.2 |
100 |
100 |
100 (.2)
= 20.00 |
100 (.2)
= 20 |
|
TOTAL |
1.0 |
|
|
64.80% |
46.40% |
OVERALL WEIGHTED
ACTUAL ACCOMPLISHMENT = 46.40%
OVERALL PROJECT SLIPPAGE = 46.40% - 64.80% = (18.40%)
|