Viewing Results 1 - 10 of 13 Record(s).   « Previous  1  2  Next » 
Rows per Page
 

a) Project Title
b) Agency
c) Location

SCHEDULE
a) Start Date
b) Completion Date
FINANCIAL (P'000)
PHYSICAL (%)
Remarks
Program AA Issued To Date Funding Support (%) Expenditure Expenditure Rate (%) Target Actual Slippage Performance
Unpaid Obligation Disbursement Total
1 a) San Pascual Port Development Project Port of San Pascual - Port Development Project
b) PPA-PMO-Leg
c) San Pascual, Masbate
a)
b)
0 0 0.00 0 0 0 0.00 0.00 0.00 0.00 0.00 On-going.
2 a) San Vicente Port - (RORO ports along the Central and Eastern Nautical Highway Provision of RORO ramp facilities for the existing and proposed ports.
b) PPA-PMO-Leg
c) Caramoan, Camarines Sur
a)
b)
0 0 0.00 0 0 0 0.00 0.00 25.00 25.00 0.00 On-going.
3 a) Boca Engano Port - (RORO Ports alon the Central and Eastern Nautical Highway) Provision of RORO ramp facilities for the existing and proposed ports.
b) PPA-PMO-Leg
c) Claveria, Masbate
a)
b)
0 0 0.00 0 0 0 0.00 0.00 0.00 0.00 0.00 Proposed project.
4 a) LG 0910 PMO Admininistration Building - Repair of administation office
b) PPA-PMO-Leg
c) Camalig, Albay
a)
b)
1,435 0 0.00 0 0 0 0.00 0.00 0.00 0.00 0.00 Bidded 10/4/2009. NTP received 10/15/2009
5 a) LG 1006 Port of Matnog, Sorsogon - Repair/rehabilitation of damaged/collapsed slope protection structure
b) PPA-PMO-Leg
c) Barcelona, Sorsogon
a) 07/24/2010
b) 04/21/2011
30,785 0 0.00 0 0 0 0.00 0.00 15.00 15.00 0.00 On-going.
6 a) LG 1004 Baseport Legazpi City Maintenance of Physical Port Facilities
b) PPA-PMO-Leg
c) Camalig, Albay
a) 05/22/2010
b) 07/21/2010
1,246 0 0.00 0 0 0 0.00 100.00 100.00 0.00 100.00 Completed
7 a) LG 1005 Baseport Legazpi City Energization of Newly-Installed Port Lighting System at Back-Up Area
b) PPA-PMO-Leg
c) Camalig, Albay
a) 05/22/2010
b) 07/21/2010
1,364 0 0.00 0 0 0 0.00 100.00 100.00 0.00 100.00 Completed
8 a) LG 1003 ECC Application for the Sorsogon Port Development Projects
b) PPA-PMO-Leg
c) Legazpi City, Albay
a) 06/01/2010
b) 06/30/2010
142 0 0.00 0 0 0 0.00 0.00 0.00 0.00 0.00 On-going.
9 a) LG 0909 Port of Virac - Repair of fendering system
b) PPA-PMO-Leg
c) Caramoran, Catanduanes
a) 10/30/2009
b) 01/30/2010
1,563 0 0.00 0 0 0 0.00 100.00 100.00 0.00 100.00 Completed.
10 a) LG 1001 Baseport Legazpi City - Repair of damaged PCCP and fender system at berth No2. 1 & 2
b) PPA-PMO-Leg
c) Camalig, Albay
a) 03/16/2010
b) 09/17/2010
18,967 0 0.00 0 0 0 0.00 0.00 95.00 95.00 0.00 On-going.
Viewing Results 1 - 10 of 13 Record(s).   « Previous  1  2  Next » 