back to top



HOME     ABOUT US     RDC 5     LINKS    

 
EXECUTIVE SUMMARY
INTRODUCTION
TRADE &  INVESTMENT
AGRIBUSINESS
ENVIRONMENT AND NATURAL RESOURCES
HOUSING
TOURISM
INFRASTRUCTURE
FISCAL STRENGTH
LABOR
POWER AND ENERGY
POWER SECTOR REFORM
BASIC NEED
PEACE AND ORDER
PEACE PROCESS
EDUCATION
SCIENCE AND TECHNOLOGY
ANTI-CORRUPTION
GOOD GOVERNANCE

CHAPTER 9 POWER AND ENERGY

Generation

 

As of December 2006, PNOC BacMan Geothermal Production Field has supplied only a total of 151,255 tons of steam to Bacman II Botong Plant, equivalent to 8013.375 MWH of electricity.  Likewise, steam supplied to NPC for BacMan I is zero due to power plant shutdown, however, steam requirement for the power plant full capacity is available. BacMan II-Cawayan plant has been on shutdown since August. 2005. Unit 4 of BacMan 2-Botong is also on shutdown since August 1, 2006 to facilitate repair of its  RH governor valve. The destruction brought about by the two super typhoons to the power plants caused the decrease in Bicol’s power contribution to the Luzon Grid.

 

Transmission

 

The National Transmission Corporation (TransCo) is tasked to provide efficient and reliable transmission of electricity across the region. It undertakes various activities such as construction and maintenance of transmission facilities, grid interconnection and power dispatch.

               

As of CY 2006, TransCo undertook maintenance of the mainline, transmission lines and load end substation and facilities for Albay and Camarines Sur substations. District III  managed about 1,270 circuti-kilometers of transmission lines, 401.21 of which is for the 350 kV and 869.13 is for 230 kV. Transco also administered 1,108.75 megavolt-amperes (MVA) of substation capacity located at Albay, Sorsogon, Camarines Sur and Camarines Norte.

 

After the onslaught of Typhoon Milenyo,  Bicol was plunged into darkness. Not yet fully recovered from the typhoon, with a couple of barangays still in the dark, comes Reming, which brought devastation much greater than that of Milenyo.  More rehabilitation works were seen, amidst the yet unfinished rehabilitation efforts. 

 

Bicol electric cooperatives were rendered useless for they themselves need to undergo debriefing, being greatly affected by the typhoon themselves. The different electric cooperatives from all over the country, through auspices of the National Electrification Administration, joined efforts worked for the full restoration of power supply in Albay until a little short to Christmas Eve.

 

Distribution

 

The region’s electricity supply is being distributed by eleven electric cooperatives (ECs), namely: Albay Electric Cooperative; Inc. (ALECO); Camarines Norte Electic Cooperative, Inc. (CANORECO); Camarines Sur I Electric Cooperative, Inc. (CASURECO 1); Camarins Sur II Electric Cooperative, Inc.  (CASURECO II); Camarines Sur III Electric Cooperative, Inc. (CASURECO III); Camarines Sur IV Electric Cooperative, Inc. (CASURECO IV), First Catanduanes Electric Cooperative, Inc. (FICELCO); Sorsogon I Electric Cooprative, Inc. (SORECO I); Sorsogon II Electric Cooperative, Inc. (SORECO II); Masbate Electric Cooperative, Inc. (MASELCO); and Ticao Island Electric Cooperative, Inc. (TISELCO).

 

Households in the off-grid areas are also enjoying the benefits of electricity through small island power grids operated by either NPC-SPUG or Independent Power Producers (IPPs). To date, 11 diesel-based plants, one mini hydro plant with an aggregate capacity of 33.15 MW are providing the energy requirements in these areas.

 

Table 1  No. of Energized Barangays as of Dec. 2006

Electric Cooperative

Potential/ Target

Total Number of
Energized Barangays

Energization
Level (%)

ALECO

720

717

99.58

CANORECO

273

273

100

CASURECO I

309

295

95.47

CASIRECO II

259

259

100

CASURECO III

229

229

100

CASURECO IV

258

258

100

FICELCO

315

315

100

SORECO 1

253

253

100

SORECO II

288

288

100

MASELCO

434

270

62.21

TISELCO

72

46

63.89

TOTAL

3,410

3,203

93.93

                                   Source:  NEA

 

Table 2 No. of Energized Consumer Connections
as of Dec. 2006

Electric Cooperative

Potential/
Target

Total Number of
Consumer Connection

ALECO

234,300

174,093

CANORECO

98,300

73,035

CASURECO I

81,400

50,618

CASIRECO II

102,500

78,133

CASURECO III

81,300

55,154

CASURECO IV

62,400

38,904

FICELCO

46,200

38,242

SORECO 1

60,800

44,427

SORECO II

82,400

68,739

MASELCO

119,700

30,461

TISELCO

16,300

4,208

TOTAL

985,600

656,014

                                   Source:  NEA

In 2006, four barangays were energized in the area, reflecting 93.93 percent of the 3,410 total potential targets.  Meanwhile, 22,384 additional consumers were served, which brings to 656,014 the total number of consumer connections served, reflecting 66.56 percent of the potential connection target of 985,600. 

 

Among the region’s provinces, Masbate is the least energized at 62.45 percent.  The province is expected to be 100 percent energized by 2008 with the signing of the Î22.5 million French Financial Protocol in November 2004 between France and the Philippine Government.  Two French firms, namely:  Paris-Manila Technology Corporation (PAMATEC) and ETDE of Bouygues Construction will be responsible for the implementation of the electrification project.  The contract stipulates the energization of about 128 barangays by year 2008 and 90 percent household connection by 2017.  With the inclusion of Masbate as one of the recipient provinces in the Philippine Rural Electrification Service (PRES) Project, line extension program in the region will further be accelerated.

 

System Loss

 

Efforts in the reduction of the average system loss level, however, were not enough to attain the 14 percent level. A slight reduction (1.06 percent) has been attained by end of 2006, comparing it with the 2005 level.  Several factors affected the system loss performance, among these are: ECs’ non-full compliance with system loss segregation requirements; increase in power pilferages due to high power rates; and low supply voltage in some ECs.  Among the Ecs, CASURECO IV, TICELCO and ALECO registered an increase in systems loss for CY 2006.  On the other hand, SORECO 1 and CANORECO posted the biggest decline in system loss, indicating their deliberate and serious efforts to curtail this.

Table 3  System Loss Level, 2006

Name of
Distribution Utility

2005 Actual
( %)

2006 Actual
(%)

Increase/

(Reduction)

ALECO

21.26

23.31

2.05

CANORECO

15.47

11.68

(3.79)

CASURECO I

20.87

22.34

1.47

CASIRECO II

19.18

19.64

0.46

CASURECO III

24.68

21.88

(2.80)

CASURECO IV

17.43

20.29

2.86

FICELCO

13.61

15.37

1.76

SORECO 1

18.92

14.39

(4.53)

SORECO II

19.22

19.37

0.15

MASELCO

18.02

21.07

3.05

TISELCO

26.85

29.19

2.37

Average

19.59

18.53

1.06

                                   Source:  DOE

 

back to top