
|
PART
III: INFRASTRUCTURE SUPPORT FACILITIES
Chapter
20. Power Generation, Transmission and Distribution
I.
Summary
The usual wear and tear coupled by
the limited funds for rehabilitation prevented the existing
geothermal power plants from achieving its maximum
generating capacity.
The total dependable generating
capacity of the plants was only 47.87 percent of its
installed capacity. The decommissioning of plants and plant
shutdowns were also contributory to the decrease in the
generating capacity.
The privatization of the steam and
electric generation for Tiwi Geothermal Power Plant (TGPP)
resulted to a 97 percent generating capacity. This was
despite the plant’s initial commissioning in the 1970s.
Barangay energization for
cooperative-covered barangays was also at its peak in 2008
with 142 barangays energized. Energization for off-grid
barangays was also continuously undertaken through the
various energization efforts of the National Power
Corporation –Small Power Utilities Group (NPC-SPUG).
II.
Assessment
Generation
The Philippines is the second-largest producer of geothermal
energy in the world after the
United States. Bicol’s
geothermal sources, BacMan and Tiwi, are the major
contributors.
In 2008 the total dependable capacity of the generating
plants (geothermal and hydro) was 243 MW (47.87%).
This was way below the total installed capacity of 507.60 MW
(Table 20.1). From the original 504 MW installed capacity
of geothermal power plants, its dependable capacity
decreased to 239.40 MW (47.50 percent) because of plant shut
downs, decommissioning of units and other factors.
Notable was the 97 percent generating capacity achieved by
the Tiwi Geothermal Power Plant (TGPP) due to the
rehabilitation of its units, counting out two generating
units (decommissioned and for long term preservation).
Bacman, however, did not fair well with the shutting down
and deactivation of two of its units. It only achieved 9
percent dependable capacity.
Table 20.1
Status of Generation, Geothermal and Hydro, Bicol Region,
As of
December 2008
|
PLANT |
CAPACITY, MW |
|
Installed |
Dependable |
|
Geothermal |
504 |
239.4 |
|
BacMan I-1 |
55 |
0 |
|
BacMan I-2 |
55 |
0 |
|
BacMan II-1(Cawayan) |
20 |
0 |
|
BacMan II (Botong) |
20 |
13 |
|
Tiwi 1 |
60 |
59.8 |
|
Tiwi 2 |
60 |
54.04 |
|
Tiwi 3 |
60 |
0 |
|
Tiwi 4 |
60 |
0 |
|
Tiwi 5 |
57 |
56.35 |
|
Tiwi 6 |
57 |
56.21 |
|
Mini-hydro |
3.6 |
3.6 |
|
Cawayan |
0.4 |
0.4 |
|
Buhi-Barit |
2 |
2 |
|
Inarihan |
1 |
1 |
|
Yabo |
0.2 |
0.2 |
|
TOTAL |
507.60 |
243 |
Source:DOE
About 150 MW of steam was available for the Tiwi
Geothermal Power Plant (TGPP) for steam generation, as
of September 25, 2008. This was equivalent to a net
generation of 803.06 GWH for the entire complex. This
resulted to an increase in geothermal based generation
in the Luzon Grid.
BacMan Geothermal Production Field (BGPF) supplied a
total of 406,624 tons of steam to NPC’s BacMan 1 plant
and 1,011,721 tons to BacMan 2 Botong plant (Table
20.2). These were equivalent to of 30,592 and 63,432 MWH
of electricity, respectively.
Table 20.2 Steam Supply and Equivalent Generation
Statistics,
Bacman Geothermal Production Field, CY 2008
|
Plant |
Steam Supplied to NPC (tons) |
NPC Generation (KWH) |
|
Bacman 1 |
|
|
|
Unit 1 |
386,815 |
30,292,400 |
|
Unit 2 |
19,809 |
300,240 |
|
Bacman 1 Total |
406,624 |
30,592,640 |
|
Bacman 2 |
|
|
|
Cawayan |
0 |
0 |
|
Botong |
1,011,721 |
63,431,820 |
|
Bacman 2 Total |
1,011,721 |
63,431,820 |
|
Total Bacman |
1,418,345 |
94,024,460 |
Source: EDC
Status of Geothermal Generating Plants
TGPP consisted of six generating plants. Units 1, 2 and 5
achieved load range of 40 MW to 54 MW. These were based on
either steam or unit capability and on steam availability.
Unit 3 was deactivated/shutdown in November 2006. This was
under long term preservation by Asset Preservation
Department (APD) of the NPC. Unit 4 was decommissioned on
the 1st Amendment of the NPC/PGI/PSALM
compromised agreement under section 7.1c dated October 13,
2003. Unit 6 was shutdown due to Chevron’s request for
steam field repair.
Bacman 1 Unit 2 was shutdown in December 2005 due to turbine
bearing vibration. It was synchronized in February 2008 but
tripped again. The unit therefore remained on shutdown.
BacMan 2-Cawayan plant was also on shutdown due to machinery
breakdown.
Based on the stored heat capacity of the blocks in Manito
and Inang Maharang, a 40 MW development in the Kayabon area
could be confirmed through exploratory drilling. The Energy
Development Corporation (EDC) scheduled the drilling of 4-6
exploratory wells in Kayabon area in September 2008 but was
deferred due to the current global financial crisis.
Privatization of NPC’s remaining assets was undertaken
during the year. The steam generation component of the
Philippine National Oil Company (PNOC) was privatized.
Steam generation is now being undertaken by the EDC
specifically for BGPF.
The Tiwi-Macban Geothermal Power Package was successfully
bid out in July 2008. The notice of award was issued and
the certificate of affectivity was handed over to AP
Renewables, Inc. in August 2008. The
Power Sector Assets and Liabilities Management Corporation (PSALM)
would continue with the selling of NPC’s decommissioned
power plants and non-operating assets.
Transmission
The
PSALM would formally turn over in January 2009 the 25-year
concession of the National Transmission Corporation (TransCo)
to the National Grid Corporation of the Philippines (NGCP).
Distribution
Under the barangay energization, the sub-sector aimed to
cover the remaining barangays in order to achieve the 100
percent energization in the region.
In 2008, 98.50 percent of barangays or 4.4 percent increase
compared to the previous year was energized. This was
equivalent to 3,359 barangays against the 3,410 target
potential barangays (Table 20.3).
The province of Masbate served by Masbate Electric
Cooperative, Inc, and Ticao Island Electric Cooperative,
Inc. had the least energized barangays at 94.70 percent and
81.94 percent, respectively.
A total of 142 barangays were energized with a cumulative
accomplishment of 175 barangyas (60.76%) from year 2004.
There was therefore a significant increase in terms of newly
energized barangays in 2008.
The energization of off-grid barangays in the provinces of
Masbate and Catanduanes was undertaken by the National Power
Corporation-Small Power Utilities Group (NPC-SPUG). These
were the non-cooperative covered barangays.
Table 20.3 Barangay Energization, Bicol Region, 2007 and 2008
|
Electric
Cooperative |
Poten-tial |
Barangays Energized |
Unener-gized
Brgys |
|
2007 |
% |
2008 |
% |
|
Albay Electric Cooperative, Inc. |
720 |
718 |
99.72 |
718 |
99.72 |
2 |
|
Camarines Norte Electric Cooperative, Inc. |
273 |
273 |
100 |
273 |
100 |
0 |
|
Camarines Sur I Electric Cooperative, Inc. |
309 |
295 |
95.47 |
296 |
95.79 |
13 |
|
Camarines Sur II Electric Cooperative, Inc. |
259 |
259 |
100 |
259 |
100 |
0 |
|
Camarines Sur III Electric Cooperative, Inc. |
229 |
229 |
100 |
229 |
100 |
0 |
|
Camarines Sur IV Electric Cooperative, Inc. |
258 |
258 |
100 |
258 |
100 |
0 |
|
First Catanduanes Electric Cooperative, Inc. |
315 |
315 |
100 |
315 |
100 |
0 |
|
Masbate Electric Cooperative, Inc. |
434 |
283 |
65.21 |
411 |
94.70 |
23 |
|
Ticao Island Electric Cooperative, Inc. |
72 |
46 |
63.89 |
59 |
81.94 |
13 |
|
Sorsogon I Electric Cooperative, Inc. |
253 |
253 |
100 |
253 |
100 |
0 |
|
Sorsogon II Electric Cooperative, Inc. |
288 |
288 |
100 |
288 |
100 |
0 |
|
TOTAL |
3,410 |
3,217 |
94.34 |
3,359 |
98.50 |
51 |
Source: NEA
NPC-SPUG continued the Philippine Rural Electrification
Service (PRES) Project. It involved the sales, survey,
design, procurement and construction of PV solar home
and/or diesel mini-grid system in 114 barangays in
mainland Masbate and 14 barangays in Ticao Island. The
Project also aims to energize 26 barangays of the
municipalities of Claveria, San Pascual, San Fernando
and San Jacinto in Masbate. The notices to proceed are
for issuance to Power Dimension, Inc.
As of December 2008, installation of solar home systems
in 5,126 households in 107 barangays in Masbate and
Ticao islands was undertaken. The construction of the
140 mini-grid systems in 100 barangays started in
November 2008. Each mini-grid system was composed of
diesel generating set (7 or 15 kVA), low voltage (LV)
distribution line system and house wiring connection.
The project is expected to be completed in August 2009.
System Loss
The 11 electric cooperatives (ECs) serving Bicol
consumers incurred an average of 20.66 percent system
loss. This was 3.46 percent lower compared last year but
way above the targeted 14 percent cap. The decrease on
the system losses was achieved by all the ECs except
ALECO which increased by 1.018 percent. NPC took over
the management of ALECO in 2008. Notable decrease was
achieved by SORECO I at 26.04 percent (Table 20.4).
Table
20.4 System Loss by Electric Cooperative, Bicol Region,
2007
and 2008
|
Electric Cooperative |
SYSTEM LOSS |
%Increase/(Decrease) |
|
2007 |
2008 |
|
Albay Electric Cooperative, Inc. |
24.56% |
24.81% |
1.018 |
|
Camarines Norte Electric Cooperative, Inc. |
11.94% |
11.78% |
(1.34) |
|
Camarines Sur I Electric Cooperative, Inc. |
25.82% |
22.37% |
(13.36) |
|
Camarines Sur II Electric Cooperative, Inc. |
21.41% |
19.22% |
(10.23) |
|
Camarines Sur III Electric Cooperative, Inc. |
28.32% |
24.26% |
(14.34) |
|
Camarines Sur IV Electric Cooperative, Inc. |
20.09% |
18.91% |
(5.87) |
|
First Catanduanes Electric Cooperative, Inc. |
14.09% |
14.14% |
(0.35) |
|
Masbate Electric Cooperative, Inc. |
22.73% |
21.11% |
(7.13) |
|
Ticao Island Electric Cooperative, Inc. |
24.90% |
24.25% |
(2.61) |
|
Sorsogon I Electric Cooperative, Inc. |
20.47% |
15.14% |
(26.04) |
|
Sorsogon II Electric Cooperative, Inc. |
21.00% |
20.82% |
(0.86) |
|
Average |
21.40% |
20.66% |
(3.46)_ |
Source: NEA
In August 2008, the Energy Regulatory Commission (ERC)
set the draft resolution adopting a new system loss
cap for distribution utilities (DUs). The draft
resolution provided that the electricity consumption
of a DU be treated as an expense and not as part of
system loss. Also, to lower the maximum recoverable
rate of system loss from 9.5 percent to 8 percent
for private DUs (or PUs) and from 14 percent to 11
percent for ECs based on the total kilowatt-hour
generated, purchased and distributed. The existing
system loss caps for PUs and ECs were not adjusted
since 1999 and 2000 for PUs and ECs, respectively.
Public consultations on the draft resolution were
held in August and September. The ERC is evaluating
the various stakeholders’ views for consideration in
the finalization of the draft resolution.
III.
Prospects and Trends for 2009
With the privatization of the generation and transmission
assets a better performance from the energy sector,
specifically the generation sub-sector, is expected. Better
power supply and better services to the end-users is
anticipated.
The clamor for lower power rates, with Bicol
being a contributor to the Luzon grid, still persists.
This, however, will require policy decision with the
existing one grid policy.
Increased geothermal exploration and production activities
are targeted to address the low performance of the existing
plants. The BacMan target expansions will be composed of
three geothermal steam production and power plant
construction and operation projects, i.e. the Kayabon at the
Manito side and Rangas and Tanawon at the Sorsogon sector
with a combined target of 120 megawatts or 40 megawatts
each. Of the 40 megawatt output of the plant, 20-megawatts
of Kayabon project will be supplied to Albay by way of a
transmission scheme. The scheme will lower the power rate
in the province by more than 50 percent since it will
exclude extra charges being imposed by the cooperative and
the NPC. The other 20-megawatt will go to the Luzon Grid.
EDC is also open to the same scheme of power supply costing
and distribution in Sorsogon which will host the Tanawon and
Rangas expansion projects. For TGPP, steam generation is
expected to increase by 10 percent or 165 MW in 2009 with
the on-going drilling of two additional wells.
The NPC is considering a bold measure called “Island
Operations” to save Bicol from being disconnected from the
rest of the Luzon grid due to damaged transmission towers
especially after typhoons. Island operations mean cutting
off the Bicol region from the rest of the Luzon grid and
providing it with dedicated power source which will make
Bicol less prone to transmission-related power outages.
DOE will still continue to increase and
accelerate access to electricity services in unenergized
barangays. It will pursue to energize the remaining 51
electric-cooperative covered barangays and the 32 non-EC
covered barangays to achieve total barangay electrification
in 2010.
As part of the expanded rural
electrification program, missionary and off-grid
electrification will be implemented through the extension of
distribution lines of electric cooperatives or installation
of mini or micro-grids or decentralized systems in the small
islands and unviable areas. The component projects are SPUG’s diesel micro-grid projects in Camarnes Sur and
Masbate. In the Missionary Electrification Development Plan
(2009-2013), it intends to increase the existing service
hours in Batan Island, Rapu-Rapu, Albay from 12 hours to 18
hours in 2009 and to 24 hours in 2013. Service hours for
mainland Rapu-Rapu, Albay is targeted to be increased from
18 to 24 hours by 2009. The PRES project in Masbate will
still be pursued. Capacity additions of 0.30 MW is also
targeted in Ticao area in 2009 and 2011.
back to
top
|