back to top



HOME     ABOUT US     RDC 5     LINKS    

 
FOREWORD
ACKNOWLEDGEMENT
EXECUTIVE SUMMARY
MACRO ECONOMIC ASSESSMENT

PART I:  RESPONDING TO THE BASIC NEEDS

CHAPTER 1: HEALTH
CHAPTER 2:  NUTRITION
CHAPTER 3: FAMILY PLANNING
CHAPTER 4:  BASIC AND TERTIARY EDUCATION
CHAPTER 5: SKILLS DEVELOPMENT
CHAPTER 6: HOUSING AND COMMUNITY DEVELOPMENT
CHAPTER 7:  SOCIAL WELFARE
CHAPTER 8:  LABOR WELFARE AND PROTECTION

PART II:  PROMOTING ECONOMIC GROWTH

CHAPTER 9:  AGRICULTURE
CHAPTER 10:  FISHERIES
CHAPTER 11:  FORESTRY
CHAPTER 12:  MINING AND QUARRYING
CHAPTER 13:  TRADE AND INDUSTRY
CHAPTER 14:  TOURISM

PART III: INFRASTRUCTURE SUPPORT FACILITIES

CHAPTER 15: LAND TRANSPORTATION
CHAPTER 16: WATER TRANSPORTATION
CHAPTER 17: AIR TRANSPORTATION
CHAPTER 18: COMMUNICATIONS
CHAPTER 19: IRRIGATION, DRAINAGE AND FLOOD CONTROL
CHAPTER 20: POWER GENERATION, TRANSMISSION AND DISTRIBUTION

PART IV: DEVELOPMENT ADMINISTRATION

CHAPTER 21: INVESTMENT PROMOTION
CHAPTER 22:  PRODUCTIVITY IMPROVEMENT
CHAPTER 23:  SCIENCE AND TECHNOLOGY
CHAPTER 24:  GOOD GOVERNANCE
CHAPTER 25:  PEACE AND ORDER
CHAPTER 26:  DISASTER MANAGEMENT
CHAPTER 27:  SUSTAINABLE DEVELOPMENT
CHAPTER 28:  GENDER AND DEVELOPMENT
CHAPTER 29:  PLAN IMPLEMENTATION
CHAPTER 30:  FINANCING THE PLAN

ANNEX A: STATUS OF TOP TEN PRIORITY PROGRAMS AND PROJECTS OF BICOL REGION

   PART III: INFRASTRUCTURE SUPPORT FACILITIES

    

     Chapter 20. Power Generation, Transmission and Distribution

I. Summary

   The usual wear and tear coupled by the limited funds for rehabilitation prevented the existing geothermal power plants from achieving its maximum generating capacity. 

 

   The total dependable generating capacity of the plants was only 47.87 percent of its installed capacity. The decommissioning of plants and plant shutdowns were also contributory to the decrease in the generating capacity.

 

   The privatization of the steam and electric generation for Tiwi Geothermal Power Plant (TGPP) resulted to a 97 percent generating capacity.  This was despite the plant’s initial commissioning in the 1970s.

 

   Barangay energization for cooperative-covered barangays was also at its peak in 2008 with 142 barangays energized. Energization for off-grid barangays was also continuously undertaken through the various energization efforts of the National Power Corporation –Small Power Utilities Group (NPC-SPUG).

 

II. Assessment

 

Generation

 

   The Philippines is the second-largest producer of geothermal energy in the world after the United States. Bicol’s geothermal sources, BacMan and Tiwi, are the major contributors. 

 

   In 2008 the total dependable capacity of the generating plants (geothermal and hydro) was 243 MW  (47.87%). This was way below the total installed capacity of 507.60 MW (Table 20.1).  From the original 504 MW installed capacity of geothermal power plants, its dependable capacity decreased to 239.40 MW (47.50 percent) because of plant shut downs, decommissioning of units and other factors.

 

   Notable was the 97 percent generating capacity achieved by  the Tiwi Geothermal Power Plant (TGPP) due to the rehabilitation of its units, counting out two generating units (decommissioned and for long term preservation).  Bacman, however, did not fair well with the shutting down and deactivation of two of its units. It only achieved 9 percent dependable capacity.

Table 20.1 Status of Generation, Geothermal and Hydro, Bicol Region,

As of December 2008

 
PLANT

CAPACITY, MW

Installed

Dependable

Geothermal

504

239.4

    BacMan I-1

55

0

    BacMan I-2

55

0

    BacMan II-1(Cawayan)

20

0

 BacMan II                       (Botong)

20

13

   Tiwi 1

60

59.8

   Tiwi 2

60

54.04

   Tiwi 3

60

0

   Tiwi 4

60

0

   Tiwi 5

57

56.35

   Tiwi 6

57

56.21

Mini-hydro

3.6

3.6

   Cawayan

0.4

0.4

   Buhi-Barit

2

2

   Inarihan

1

1

   Yabo

0.2

0.2

TOTAL

507.60

243

                      Source:DOE

   About 150 MW of steam was available for the Tiwi Geothermal Power Plant (TGPP) for steam generation, as of September 25, 2008.  This was equivalent to a net generation of 803.06 GWH for the entire complex. This resulted to an increase in geothermal based generation in the Luzon Grid.

 

   BacMan Geothermal Production Field (BGPF) supplied a total of 406,624 tons of steam to NPC’s BacMan 1 plant and 1,011,721 tons to BacMan 2 Botong plant (Table 20.2). These were equivalent to of 30,592 and 63,432 MWH of electricity, respectively. 

Table 20.2 Steam Supply and Equivalent Generation Statistics,

Bacman Geothermal Production Field, CY 2008

Plant

Steam Supplied to NPC (tons)

NPC Generation (KWH)

Bacman 1

 

 

     Unit 1

386,815

30,292,400

     Unit 2

19,809

300,240

Bacman 1 Total

406,624

30,592,640

Bacman 2

 

 

     Cawayan

0

0

     Botong

1,011,721

63,431,820

Bacman 2 Total

1,011,721

63,431,820

Total Bacman

1,418,345

94,024,460

                               Source:  EDC

Status of Geothermal Generating Plants

   TGPP consisted of six generating plants. Units 1, 2 and 5 achieved load range of 40 MW to 54 MW. These were based on either steam or unit capability and on steam availability.  Unit 3 was deactivated/shutdown in November 2006.  This was under long term preservation by Asset Preservation Department (APD) of the NPC.  Unit 4 was decommissioned on the 1st Amendment of the NPC/PGI/PSALM compromised agreement under section 7.1c dated October 13, 2003.  Unit 6 was shutdown due to Chevron’s request for steam field repair. 

 

   Bacman 1 Unit 2 was shutdown in December 2005 due to turbine bearing vibration.  It was synchronized in February 2008 but tripped again. The unit therefore remained on shutdown. BacMan 2-Cawayan plant was also on shutdown due to machinery breakdown. 

 

   Based on the stored heat capacity of the blocks in Manito and Inang Maharang, a 40 MW development in the Kayabon area could be confirmed through exploratory drilling.  The Energy Development Corporation (EDC) scheduled the drilling of 4-6 exploratory wells in Kayabon area in September 2008 but was deferred due to the current global financial crisis.

 

   Privatization of NPC’s remaining assets was undertaken during the year.  The steam generation component of the Philippine National Oil Company (PNOC) was privatized.  Steam generation is now being undertaken by the EDC specifically for BGPF.

 

   The Tiwi-Macban Geothermal Power Package was successfully bid out in July 2008.  The notice of award was issued and the certificate of affectivity was handed over to AP Renewables, Inc. in August 2008.  The Power Sector Assets and Liabilities Management Corporation (PSALM) would continue with the selling of NPC’s decommissioned power plants and non-operating assets.

 Transmission

   The PSALM would formally turn over in January 2009 the 25-year concession of the National Transmission Corporation (TransCo) to the National Grid Corporation of the Philippines (NGCP).

 Distribution

   Under the barangay energization, the sub-sector aimed to cover the remaining barangays in order to achieve the 100 percent energization in the region.

 

   In 2008, 98.50 percent of barangays or 4.4 percent increase compared to the previous year was energized. This was equivalent to 3,359 barangays against the 3,410 target potential barangays (Table 20.3).

The province of Masbate served by Masbate Electric Cooperative, Inc, and Ticao Island Electric Cooperative, Inc. had the least energized barangays at 94.70 percent and 81.94 percent, respectively. 

 

   A total of 142 barangays were energized with a cumulative accomplishment of 175 barangyas (60.76%) from year 2004.  There was therefore a significant increase in terms of newly energized barangays in 2008.   

 

   The energization of off-grid barangays in the provinces of Masbate and Catanduanes was undertaken by the National Power Corporation-Small Power Utilities Group (NPC-SPUG).  These were the non-cooperative covered barangays.

Table 20.3 Barangay Energization, Bicol Region, 2007 and 2008

Electric
Cooperative

Poten-tial

Barangays Energized

Unener-gized
Brgys

2007

%

2008

%

Albay Electric Cooperative, Inc.

720

718

99.72

718

99.72

2

Camarines Norte Electric Cooperative, Inc.

273

273

100

273

100

0

Camarines Sur I Electric Cooperative, Inc.

309

295

95.47

296

95.79

13

Camarines Sur II Electric Cooperative, Inc.

259

259

100

259

100

0

Camarines Sur III Electric Cooperative, Inc.

229

229

100

229

100

0

Camarines Sur IV Electric Cooperative, Inc.

258

258

100

258

100

0

First Catanduanes Electric Cooperative, Inc.

315

315

100

315

100

0

Masbate Electric Cooperative, Inc.

434

283

65.21

411

94.70

23

Ticao Island Electric Cooperative, Inc.

72

46

63.89

59

81.94

13

Sorsogon I Electric Cooperative, Inc.

253

253

100

253

100

0

Sorsogon II Electric Cooperative, Inc.

288

288

100

288

100

0

TOTAL

3,410

3,217

94.34

3,359

98.50

51

                       Source:  NEA

   NPC-SPUG continued the Philippine Rural Electrification Service (PRES) Project. It involved the sales, survey, design, procurement and construction of PV solar home and/or diesel mini-grid system in 114 barangays in mainland Masbate and 14 barangays in Ticao Island. The Project also aims to energize 26 barangays of the municipalities of Claveria, San Pascual, San Fernando and San Jacinto in Masbate.  The notices to proceed are for issuance to Power Dimension, Inc.

 

   As of December 2008, installation of solar home systems in 5,126 households in 107 barangays in Masbate and Ticao islands was undertaken.  The construction of the 140 mini-grid systems in 100 barangays started in November 2008.  Each mini-grid system was composed of diesel generating set (7 or 15 kVA), low voltage (LV) distribution line system and house wiring connection.  The project is expected to be completed in August 2009.

 

System Loss

   The 11 electric cooperatives (ECs) serving Bicol consumers incurred an average of 20.66 percent system loss. This was 3.46 percent lower compared last year but way above the targeted 14 percent cap. The decrease on the system losses was achieved by all the ECs except ALECO which increased by 1.018 percent. NPC took over the management of ALECO in 2008.  Notable decrease was achieved by SORECO I at 26.04 percent (Table 20.4).

Table 20.4 System Loss by Electric Cooperative, Bicol Region,

2007 and 2008

               
Electric Cooperative

SYSTEM LOSS

%Increase/(Decrease)

2007

2008

Albay Electric Cooperative, Inc.

24.56%

24.81%

1.018

Camarines Norte Electric Cooperative, Inc.

11.94%

11.78%

(1.34)

Camarines Sur I Electric Cooperative, Inc.

25.82%

22.37%

(13.36)

Camarines Sur II Electric Cooperative, Inc.

21.41%

19.22%

(10.23)

Camarines Sur III Electric Cooperative, Inc.

28.32%

24.26%

(14.34)

Camarines Sur IV Electric Cooperative, Inc.

20.09%

18.91%

(5.87)

First Catanduanes Electric Cooperative, Inc.

14.09%

14.14%

(0.35)

Masbate Electric Cooperative, Inc.

22.73%

21.11%

(7.13)

Ticao Island Electric Cooperative, Inc.

24.90%

24.25%

(2.61)

Sorsogon I Electric Cooperative, Inc.

20.47%

15.14%

(26.04)

Sorsogon II Electric Cooperative, Inc.

21.00%

20.82%

(0.86)

Average

21.40%

20.66%

(3.46)_

                                 Source:  NEA

   In August 2008, the Energy Regulatory Commission (ERC) set the draft resolution adopting a new system loss cap for distribution utilities (DUs).   The draft resolution provided that the electricity consumption of a DU be treated as an expense and not as part of system loss. Also, to lower the maximum recoverable rate of system loss from 9.5 percent to 8 percent for private DUs (or PUs) and from 14 percent to 11 percent for ECs based on the total kilowatt-hour generated, purchased and distributed.  The existing system loss caps for PUs and ECs were not adjusted since 1999 and 2000 for PUs and ECs, respectively.

 

   Public consultations on the draft resolution were held in August and September. The ERC is evaluating the various stakeholders’ views for consideration in the finalization of the draft resolution.

III.  Prospects and Trends for 2009 

 

   With the privatization of the generation and transmission assets a better performance from the energy sector, specifically the generation sub-sector, is expected.  Better power supply and better services to the end-users is anticipated.

               

   The clamor for lower power rates, with Bicol being a contributor to the Luzon grid, still persists.  This, however, will require policy decision with the existing one grid policy.

 

   Increased geothermal exploration and production activities are targeted to address the low performance of the existing plants. The BacMan target expansions will be composed of three geothermal steam production and power plant construction and operation projects, i.e. the Kayabon at the Manito side and Rangas and Tanawon at the Sorsogon sector with a combined target of 120 megawatts or 40 megawatts each. Of the 40 megawatt output of the plant, 20-megawatts of Kayabon project will be supplied to Albay by way of a transmission scheme.  The scheme will lower the power rate in the province by more than 50 percent since it will exclude extra charges being imposed by the cooperative and the NPC. The other 20-megawatt will go to the Luzon Grid. EDC is also open to the same scheme of power supply costing and distribution in Sorsogon which will host the Tanawon and Rangas expansion projects.  For TGPP, steam generation is expected to increase by 10 percent or 165 MW in 2009 with the on-going drilling of two additional wells. 

 

   The NPC is considering a bold measure called “Island Operations” to save Bicol from being disconnected from the rest of the Luzon grid due to damaged transmission towers especially after typhoons.  Island operations mean cutting off the Bicol region from the rest of the Luzon grid and providing it with dedicated power source which will make Bicol less prone to transmission-related power outages.

 

   DOE will still continue to increase and accelerate access to electricity services in unenergized barangays.  It will pursue to energize the remaining 51 electric-cooperative covered barangays and the 32 non-EC covered barangays to achieve total barangay electrification in 2010.

 

   As part of the expanded rural electrification program, missionary and off-grid electrification will be implemented through the extension of distribution lines of electric cooperatives or installation of mini or micro-grids or decentralized systems in the small islands and unviable areas.  The component projects are SPUG’s diesel micro-grid projects in Camarnes Sur and Masbate. In the Missionary Electrification Development Plan (2009-2013), it intends to increase the existing service hours in Batan Island, Rapu-Rapu, Albay from 12 hours to 18 hours in 2009 and to 24 hours in 2013.  Service hours for mainland Rapu-Rapu, Albay is targeted to be increased from 18 to 24 hours by 2009. The PRES project in Masbate will still be pursued. Capacity additions of 0.30 MW is also targeted in Ticao area in 2009 and 2011.

back to top